Works in Progress 23 to 29 November 2009
Suburb Street or Locality Description of Works
Avoca Cape Three Points Retaining Wall -  Clear trees & set up site
Forresters Beach  Forresters Beach Road  Retaining wall - Construct Wall 
Kincumber  Seabreeze Avenue  Construction of public toilet facility & BBQ & shelter installation - Painting of facility 
Gosford Donnison Street & Henry Parry Drive Kibble Park upgrade stage 5
Green Point Avoca Drive & Lakewood Avenue Road intersection construction - Handrail
Pearl Beach  Pearl Beach Rock Pool  Cliff face stabilisation  with mesh &  shotcrete - Works commencing
Point Clare Goodaywang Reserve Toilet block, BBQ facilities & signage to be installed
Point Clare  Between Lorraine Ave & Scott Street  Planned Resurfacing 
Saratoga   Jirramba Avenue  Emergency storage tank - In progress
Saratoga  Mimosa Ave, Centenia Ave & Moonah Ave  Watermain renewal - Investigation 
Terrigal  Barnhill Road  Road Reconstruction between Grosvenor Road & Scenic Highway 
Terrigal Terrigal Haven  Foreshore stablisation works - stage 2 wall construction - Final landscaping & pathways
Terrigal   Yerang Close  Watermain renewal - Investigation 
Terrigal  Grovenor Road & Glen View Close  Watermain renewal - Investigation 
Umina   Mt Ettalong   Road reconstruction - Drainage 
Umina   Melbourne & Adelaide Ave  Establish Roundabout 
Wamberal  Ocean View Drive  Watermain renewal
Woy Woy  Springwood & Gallipoli  Road Construction - Drainage 
Wyoming  Turpentine Road  Installation of raised threshold
Yattalunga Davistown Road  Road reconstruction - Finalise Stage